SWMS template for high risk construction work
This SWMS template helps a builder or trade business plan high risk construction work before it starts. It sets out each step, its hazards and controls, the checks and the crew's sign-on.
Inside the safe work method statement template
It writes the job as steps in the order the work happens, each with its hazards, risks and controls. A filled-in roofing step is the SWMS example to copy from.
Safe work method statement
This SWMS is for [Business name], ABN [Business ABN]. It covers [The high risk construction work] at [Site address].
The principal contractor is [Principal contractor, if the work is part of a construction project]. The WHS management plan for the project is [WHS management plan title and date, if any].
It was prepared on [Date prepared] by [Name and role of the person who prepared it]. The workers consulted were [Workers and health and safety representative consulted].
The work starts on [Start date]. The person who supervises it on site is [Site supervisor name and phone].
1. The high risk construction work
Tick each kind of high risk construction work this job involves.
- A risk of a person falling more than 2 metres
- Work on a telecommunication tower
- Demolition of a load-bearing element, or one related to the physical integrity of the structure
- Disturbance, or likely disturbance, of asbestos
- Structural alterations or repairs that need temporary support to prevent collapse
- Work in or near a confined space
- Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel
- Use of explosives
- Work on or near pressurised gas distribution mains or piping
- Work on or near chemical, fuel or refrigerant lines
- Work on or near energised electrical installations or services
- Work in an area that may have a contaminated or flammable atmosphere
- Tilt-up or precast concrete
- Work on, in or next to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians
- Work in an area with any movement of powered mobile plant
- Work in an area with artificial extremes of temperature
- Work in or near water or other liquid that involves a risk of drowning
- Diving work
A SWMS is required for high risk construction work. For other work, a risk assessment or a safe work procedure may suit better.
2. Before the work starts
- Each worker holds [Licences, tickets and training the work needs].
- The plant and equipment is [Plant and equipment to be used], checked on [Date plant checked].
- Each worker wears [Personal protective equipment].
- The emergency arrangements are [First aid, rescue and emergency contacts].
- A copy was given to the principal contractor on [Date copy given], if the work is part of a construction project.
- The crew was taken through this SWMS on [Date of briefing] and has signed on in section 5.
3. Job steps, hazards and controls
Write the work as steps in the order they happen. Fill in one step section for each step.
List each step's controls from the top of the hierarchy down. Eliminate the risk so far as is reasonably practicable. If that is not reasonably practicable, minimise the risk, so far as is reasonably practicable, by substituting the hazard, isolating it or using engineering controls, then administrative controls, and personal protective equipment last.
Step 1. [Name of the job step]
- The step is [What is done, and with what plant or tools].
- Its hazards are [Hazards in this step].
- The risks they create are [Who could be harmed, and how].
- The controls are [Controls, from the top of the hierarchy down].
- [Person responsible] puts the controls in place and checks them by [How and when the controls are checked].
- The risk that remains is [High, medium or low].
Copy this section for each step and number it Step 2, Step 3 and so on.
Example. A filled-in step
This SWMS example is ours, for fixing roof sheets on a single-storey house extension where a person could fall more than 2 metres. It is an example, not the answer for your site.
- The step is laying and fixing metal roof sheets from a scaffold and the roof frame.
- Its hazards are falls from the roof edge or through the frame, dropped sheets, wind catching a sheet and sharp sheet edges.
- The risks they create are serious injury to a roofer from a fall, and to people below from falling sheets or tools.
- The controls are edge protection on every open edge, safety mesh over the frame and an exclusion zone below. Sheets are not lifted in strong wind, and roofers wear cut-resistant gloves.
- The site supervisor checks the edge protection and the mesh each morning before work starts, and records it in the site diary.
- The risk that remains is medium.
4. Checking and reviewing this SWMS
- The supervisor checks the work against this SWMS by [How and how often the work is checked].
- Work not done as this SWMS says stops at once, or as soon as it is safe, and restarts only as this SWMS says.
- This SWMS is reviewed, and changed as needed, whenever a control measure is reviewed and changed, and in any case by [Review date].
Review a control when it does not control the risk so far as is reasonably practicable, or when a new hazard or risk is found. Review it before a change at the site that is likely to bring a new or different risk the control may not effectively control. Review it too when consultation shows a review is needed, or when a health and safety representative requests one under r 38(4). A representative may request one when they reasonably believe one of those reasons affects, or may affect, the health and safety of their work group, and the control has not been adequately reviewed.
5. Crew sign-on
I have read this SWMS, or had it explained to me, and I will follow it.
- [Worker name 1] signed [Signature 1] on [Date signed 1].
- [Worker name 2] signed [Signature 2] on [Date signed 2].
- [Worker name 3] signed [Signature 3] on [Date signed 3].
Add a line for every worker who does the work, including anyone who joins the job later.
6. Keeping this SWMS
- Keep a copy until the high risk construction work is finished.
- If a notifiable incident happens in connection with the work, keep it for at least 2 years after the incident.
- For as long as you keep it, keep a copy where every worker doing the work can readily get to it, and available for inspection.
Approved by [Name and position of the person approving] on [Date approved].
How we use a SWMS
When we help a builder with a SWMS, we walk the job with the crew and write the steps in order. We check each control against the hierarchy before anyone signs on.
Fill in the SWMS form together
Consult the crew, and their health and safety representative if they have one.
One section a step
Name the person who checks each control.
Brief the crew first
Take them through it before work starts, and keep a copy on site.
Change it when work changes
Stop work that strays from it, review it, then brief the crew again.
SWMS and the WHS Regulations
From the model WHS Regulations (Compilation No. 28, 25 March 2025), read 19 November 2026. Each state and territory has its own, Victoria under its own Act, so check yours.
- When a SWMS is needed: Before high risk construction work starts, a business carrying it out must ensure a SWMS is prepared, or was prepared by another person (r 299(1)).
- What it must say: The work, its hazards and risks, the control measures, and how they are put in place, monitored and reviewed (r 299(2)).
- Written for the site: Take account of the site and any WHS management plan. Set it out so its users can readily get to and understand it (r 299(3)).
- Follow it, or stop: Make sure the work follows it. If not, stop at once or as soon as it is safe, and resume only as it says (r 300).
- A copy to the principal contractor: On a construction project ($250,000 or more), give it to the principal contractor before the work starts (rr 292, 301).
- Review it: Review it, and revise it as necessary, when its control measures are revised (r 302).
- How long to keep it: Until the work is completed, or at least 2 years after a notifiable incident in it, within reach of its workers (r 303).
- Consult your workers: Consult affected workers, so far as is reasonably practicable, when identifying hazards, assessing risks and deciding controls. Involve any health and safety representative (ss 47 to 49).
Get the template
Free with an account. Sign up and verify your email to download.
SWMS template for high risk construction work
Word: editable, fields marked.
PDF: ready to print.
Downloads open soon.
You are signed in. Choose a file to download.
Want it tailored?
Talk it through before work starts. We check your steps, hazards and controls against the regulations where you work.
General information only. This page and its template summarise Australian work health and safety law as at the date they were last reviewed. They do not take your circumstances into account and are not legal advice.