A client or principal contractor has asked for your SWMS before your team starts work. This guide explains what a safe work method statement is, when the law requires one, what it must say and how long to keep it.

Short answer

A SWMS is a safe work method statement. It sets out how high risk construction work will be done safely. Before that work starts, the business doing it must make sure one has been prepared (r 299(1)). It names the work, its hazards and risks, the controls, and how they are checked (r 299(2)).

How we can help Our advisers check your SWMS against the work on site, then tell you what to fix before work starts.
WHS policies and documents

What is a SWMS?

SWMS stands for safe work method statement. If you searched for the swms meaning, or asked what is swms, this is the answer. It is a written plan for one task of high risk construction work, done on one site.

A SWMS is not your safety policy and not a risk register for the whole business. It is narrower and more practical. A worker should be able to read it before the task and know how the job will be done safely.

The rules are in the WHS Regulations, not the WHS Act. This guide quotes the model regulations. Each state and territory makes its own, so check the version where the work is done. Our work health and safety laws guide names the law in each.

When is a SWMS required?

You need a SWMS before high risk construction work starts (r 299(1)). The duty sits with each business whose work includes that work.

Construction work is a wide term. It covers building, altering, renovating, repairing, maintaining, demolishing or dismantling a structure (r 289(1)). It also covers excavation and site preparation linked to that work (r 289(2)).

High risk construction work is a set list of 18 kinds of construction work (r 291). It includes work that:

  • involves a risk of a person falling more than 2 metres
  • is in or near a shaft or trench deeper than 1.5 metres, or a tunnel
  • is on or near energised electrical installations or services
  • involves, or is likely to involve, disturbing asbestos
  • demolishes a load-bearing element, or one tied to the structure's physical integrity
  • is in or near a confined space
  • is in an area where powered mobile plant moves
  • is on or next to a road or railway in use by traffic other than pedestrians

If the task is on the list, you need a SWMS whatever the size of the job. If it is not, the regulations do not ask for one. You must still manage the task's risks (r 35).

Construction swms, electrical swms and other trades

A construction swms is simply one written for building work on the list. Trades often keep one for each task they repeat.

An electrical swms is common because work near energised installations is on the list. A carpentry swms is often needed for roof framing or other work at height. A plumber working in a trench deeper than 1.5 metres needs one too.

A statement written for one site is a starting point for the next. Change it for the conditions of each new site before work starts (r 299(3)).

What a SWMS must include

The regulations set four things a SWMS must do (r 299(2)):

  • identify the work that is high risk construction work
  • specify the hazards of that work and the risks they cause
  • describe the measures that will control those risks
  • describe how the controls will be implemented, monitored and reviewed

It must also take into account the conditions at the workplace that may affect how the work is done (r 299(3)). On a construction project it must take into account the project's WHS management plan. It must be set out so the people who use it can read and understand it (r 299(3)(b)).

Pick controls in the order the law sets. Remove the risk if you can. If you cannot, substitute, isolate or engineer it out, then use procedures, then personal protective equipment (r 36). Our guide to what a hazard is explains that order.

Who prepares a SWMS?

The business carrying out the work must make sure a SWMS is prepared, or has already been prepared by another person (r 299(1)). In practice the contractor whose workers do the task writes it with them.

You must consult the workers who do the work when you identify its hazards and decide how to control them (s 49(a), (b)). They know where the job goes wrong.

If the work is part of a construction project, give a copy to the principal contractor before the work starts (r 301).

Following and reviewing the SWMS

Writing the statement is half the duty. You must put arrangements in place so the work is done the way the SWMS says (r 300(1)).

If the work is not being done that way, stop it immediately or as soon as it is safe to do so. Restart it only in line with the statement (r 300(2)).

Review and, if needed, revise the SWMS whenever its controls are revised (r 302). The controls must be reviewed when they do not control the risk, before a change at the workplace, or when a new hazard is found (r 38(2)). They must also be reviewed when consultation shows a need, or when a health and safety representative asks.

How long to keep a SWMS

Keep a copy of the SWMS until the high risk construction work it covers is finished (r 303(1)). If a notifiable incident happens in connection with that work, keep it for at least 2 years after the incident (r 303(2)).

While you hold it, a copy must be readily accessible to every worker you engage to do the work (r 303(3)). A copy in the site office or on a shared device the crew can open meets that aim.

The difference between a SWMS and a JSA

A JSA, or job safety analysis, is a common name for a check of a task's steps and risks. The regulations quoted here do not use the term.

A JSA can feed into a SWMS, and some businesses use one for work that is not on the list. For high risk construction work, the document must do the four things a SWMS must do (r 299(2)), whatever it is called.

How we help with a SWMS

When a builder or trade business calls us about a SWMS, we first check that the statement names the task the crew will actually do. We then test each control against the order the law sets, and ask how the crew was taken through it.

We can review a statement before a tender or a site start, or write a set for the tasks you repeat. For the wider system, see our risk assessment guide.

SWMS questions

SWMS stands for safe work method statement. It is a document that sets out how a task of high risk construction work will be done safely. It names the work, its hazards and risks, the controls and how they will be checked (r 299(2)). It must be ready before the work starts (r 299(1)).

In construction, a SWMS is the plan for a high risk task. Examples are work with a fall risk over 2 metres, work in a trench deeper than 1.5 metres and work near live electrical services. These are on the list of 18 kinds of high risk construction work (r 291). Each business doing such a task needs one.

Its purpose is to plan a high risk task before it starts and to give the crew a clear method to follow. The business must put arrangements in place so the work is done as the SWMS says (r 300(1)). If it is not, the work stops and restarts only in line with it (r 300(2)).

It is the written safe work method statement itself, on paper or on a device. It must be set out so the workers who use it can read and understand it (r 299(3)(b)). Keep it readily accessible to every worker engaged to do the task while you hold it (r 303(3)).

A SWMS is required before high risk construction work starts (r 299(1)). That means construction work on the set list (r 291). Examples are work with a fall risk over 2 metres, work that may disturb asbestos and work in a confined space. For other construction work you still manage the risks, but no SWMS is required.

The business doing the high risk construction work must make sure a SWMS is prepared, or has already been prepared by someone else (r 299(1)). The workers who do the task should be consulted on its hazards and controls (s 49). On a construction project the principal contractor gets a copy (r 301).

A JSA, or job safety analysis, is a common name for a check of a task's steps and risks. A SWMS is the document the regulations require for high risk construction work, and it must do four set things (r 299(2)). A JSA can feed into a SWMS, but it only meets the duty if it does those four things.

Keep it until the high risk construction work it covers is finished (r 303(1)). If a notifiable incident happens in connection with the work, keep it for at least 2 years after the incident (r 303(2)). Until then, a copy must stay readily accessible to the workers doing the task (r 303(3)).

How we can help

WHS policies and documents

Safe work method statements reviewed or written for the tasks your crews repeat.

Starting high risk construction work? Ask about writing a SWMS

Tell us the work, the site and the crew doing it, and an adviser will reply within 24 hours. Before the work starts, call our 24/7 HR advice line on 1300 144 002.

Call 1300 144 002

General information only. This guide summarises Australian work health and safety law as at its last review. It does not cover your circumstances and is not legal advice.