# SWMS template for high risk construction work

> A free SWMS template in Word and PDF. Set out each step of high risk construction work with its hazards and controls, then review it and sign on the crew.

This SWMS template helps a builder or trade business plan high risk construction work before it starts. It sets out each step, its hazards and controls, the checks and the crew's sign-on.

## Inside the safe work method statement template

It writes the job as steps in the order the work happens, each with its hazards, risks and controls. A filled-in roofing step is the SWMS example to copy from.

### Safe work method statement

This SWMS is for [Business name], ABN [Business ABN]. It covers [The high risk construction work] at [Site address].

The principal contractor is [Principal contractor, if the work is part of a construction project]. The WHS management plan for the project is [WHS management plan title and date, if any].

It was prepared on [Date prepared] by [Name and role of the person who prepared it]. The workers consulted were [Workers and health and safety representative consulted].

The work starts on [Start date]. The person who supervises it on site is [Site supervisor name and phone].

### 1. The high risk construction work

Tick each kind of high risk construction work this job involves.

- [ ] A risk of a person falling more than 2 metres
- [ ] Work on a telecommunication tower
- [ ] Demolition of a load-bearing element, or one related to the physical integrity of the structure
- [ ] Disturbance, or likely disturbance, of asbestos
- [ ] Structural alterations or repairs that need temporary support to prevent collapse
- [ ] Work in or near a confined space
- [ ] Work in or near a shaft or trench deeper than 1.5 metres, or a tunnel
- [ ] Use of explosives
- [ ] Work on or near pressurised gas distribution mains or piping
- [ ] Work on or near chemical, fuel or refrigerant lines
- [ ] Work on or near energised electrical installations or services
- [ ] Work in an area that may have a contaminated or flammable atmosphere
- [ ] Tilt-up or precast concrete
- [ ] Work on, in or next to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians
- [ ] Work in an area with any movement of powered mobile plant
- [ ] Work in an area with artificial extremes of temperature
- [ ] Work in or near water or other liquid that involves a risk of drowning
- [ ] Diving work

> A SWMS is required for high risk construction work. For other work, a risk assessment or a safe work procedure may suit better.

### 2. Before the work starts

- [ ] Each worker holds [Licences, tickets and training the work needs].
- [ ] The plant and equipment is [Plant and equipment to be used], checked on [Date plant checked].
- [ ] Each worker wears [Personal protective equipment].
- [ ] The emergency arrangements are [First aid, rescue and emergency contacts].
- [ ] A copy was given to the principal contractor on [Date copy given], if the work is part of a construction project.
- [ ] The crew was taken through this SWMS on [Date of briefing] and has signed on in section 5.

### 3. Job steps, hazards and controls

Write the work as steps in the order they happen. Fill in one step section for each step.

> List each step's controls from the top of the hierarchy down. Eliminate the risk so far as is reasonably practicable. If that is not reasonably practicable, minimise the risk, so far as is reasonably practicable, by substituting the hazard, isolating it or using engineering controls, then administrative controls, and personal protective equipment last.

### Step 1. [Name of the job step]

1. The step is [What is done, and with what plant or tools].
2. Its hazards are [Hazards in this step].
3. The risks they create are [Who could be harmed, and how].
4. The controls are [Controls, from the top of the hierarchy down].
5. [Person responsible] puts the controls in place and checks them by [How and when the controls are checked].
6. The risk that remains is [High, medium or low].

> Copy this section for each step and number it Step 2, Step 3 and so on.

### Example. A filled-in step

> This SWMS example is ours, for fixing roof sheets on a single-storey house extension where a person could fall more than 2 metres. It is an example, not the answer for your site.

1. The step is laying and fixing metal roof sheets from a scaffold and the roof frame.
2. Its hazards are falls from the roof edge or through the frame, dropped sheets, wind catching a sheet and sharp sheet edges.
3. The risks they create are serious injury to a roofer from a fall, and to people below from falling sheets or tools.
4. The controls are edge protection on every open edge, safety mesh over the frame and an exclusion zone below. Sheets are not lifted in strong wind, and roofers wear cut-resistant gloves.
5. The site supervisor checks the edge protection and the mesh each morning before work starts, and records it in the site diary.
6. The risk that remains is medium.

### 4. Checking and reviewing this SWMS

- [ ] The supervisor checks the work against this SWMS by [How and how often the work is checked].
- [ ] Work not done as this SWMS says stops at once, or as soon as it is safe, and restarts only as this SWMS says.
- [ ] This SWMS is reviewed, and changed as needed, whenever a control measure is reviewed and changed, and in any case by [Review date].

> Review a control when it does not control the risk so far as is reasonably practicable, or when a new hazard or risk is found. Review it before a change at the site that is likely to bring a new or different risk the control may not effectively control. Review it too when consultation shows a review is needed, or when a health and safety representative requests one under r 38(4). A representative may request one when they reasonably believe one of those reasons affects, or may affect, the health and safety of their work group, and the control has not been adequately reviewed.

### 5. Crew sign-on

I have read this SWMS, or had it explained to me, and I will follow it.

1. [Worker name 1] signed [Signature 1] on [Date signed 1].
2. [Worker name 2] signed [Signature 2] on [Date signed 2].
3. [Worker name 3] signed [Signature 3] on [Date signed 3].

> Add a line for every worker who does the work, including anyone who joins the job later.

### 6. Keeping this SWMS

- [ ] Keep a copy until the high risk construction work is finished.
- [ ] If a notifiable incident happens in connection with the work, keep it for at least 2 years after the incident.
- [ ] For as long as you keep it, keep a copy where every worker doing the work can readily get to it, and available for inspection.

Approved by [Name and position of the person approving] on [Date approved].

## How we use a SWMS

When we help a builder with a SWMS, we walk the job with the crew and write the steps in order. We check each control against the hierarchy before anyone signs on.

- Fill in the SWMS form together: Consult the crew, and their health and safety representative if they have one.
- One section a step: Name the person who checks each control.
- Brief the crew first: Take them through it before work starts, and keep a copy on site.
- Change it when work changes: Stop work that strays from it, review it, then brief the crew again.

## SWMS and the WHS Regulations

From the model WHS Regulations (Compilation No. 28, 25 March 2025), read 19 November 2026. Each state and territory has its own, Victoria under its own Act, so check yours.

- When a SWMS is needed: Before high risk construction work starts, a business carrying it out must ensure a SWMS is prepared, or was prepared by another person (r 299(1)).
- What it must say: The work, its hazards and risks, the control measures, and how they are put in place, monitored and reviewed (r 299(2)).
- Written for the site: Take account of the site and any WHS management plan. Set it out so its users can readily get to and understand it (r 299(3)).
- Follow it, or stop: Make sure the work follows it. If not, stop at once or as soon as it is safe, and resume only as it says (r 300).
- A copy to the principal contractor: On a construction project ($250,000 or more), give it to the principal contractor before the work starts (rr 292, 301).
- Review it: Review it, and revise it as necessary, when its control measures are revised (r 302).
- How long to keep it: Until the work is completed, or at least 2 years after a [notifiable incident](https://www.employmentcompass.com.au/definition/notifiable-incident) in it, within reach of its workers (r 303).
- Consult your workers: Consult affected workers, so far as is reasonably practicable, when identifying hazards, assessing risks and deciding controls. Involve any health and safety representative (ss 47 to 49).

## Get the template

Free with an account. Sign up and verify your email to download.

- Word file (.docx): Editable, fields marked.
- PDF: Ready to print.

## The guides behind it

- [SWMS (safe work method statement)](https://www.employmentcompass.com.au/guide/swms): When one is needed, and who prepares it.
- [Risk assessment](https://www.employmentcompass.com.au/guide/risk-assessment): For work that is not high risk.
- [What is a hazard?](https://www.employmentcompass.com.au/guide/hazard): The kinds of hazard to look for.
- [The WHS Act 2011](https://www.employmentcompass.com.au/guide/work-health-and-safety-laws): The duties behind the Regulations.
- [Risk assessment template](https://www.employmentcompass.com.au/templates/risk-assessment): To rate and control other risks.

## Want it tailored?

Talk it through before work starts. We check your steps, hazards and controls against the regulations where you work.

- [WHS policies and documents](https://www.employmentcompass.com.au/services/workplace-health-and-safety/whs-policies-and-documents): SWMS, safe work procedures and a WHS policy.
- [WHS consulting](https://www.employmentcompass.com.au/services/workplace-health-and-safety): Advice, audits and risk management for your business.

- [About WHS documents](https://www.employmentcompass.com.au/services/workplace-health-and-safety/whs-policies-and-documents)
- [Call 1300 144 002](tel:1300144002)

**General information only.** This page and its template summarise Australian work health and safety law as at the date they were last reviewed. They do not take your circumstances into account and are not legal advice.

---

## Facts checked on this page

- A person conducting a business or undertaking that includes the carrying out of high risk construction work must, before high risk construction work commences, ensure that a safe work method statement for the proposed work is prepared or has already been prepared by another person. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A safe work method statement must identify the work that is high risk construction work, specify hazards relating to it and the risks associated with those hazards, describe the measures to control the risks and describe how they are to be implemented, monitored and reviewed; it must be prepared taking into account all relevant matters, including circumstances at the workplace and, for work in connection with a construction project, the WHS management plan, and be set out and expressed in a way that is readily accessible and understandable to persons who use it. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- High risk construction work means construction work of 18 listed kinds, (a) to (r), among them a risk of a person falling more than 2 metres, a shaft or trench with an excavated depth greater than 1.5 metres, work on or near energised electrical installations or services, and an area with any movement of powered mobile plant; the document's checklist gives all 18. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A construction project is a project that involves construction work where the cost of the construction work is $250 000 or more. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- The person must put in place arrangements for ensuring high risk construction work is carried out in accordance with the safe work method statement; if it is not, the person must ensure the work is stopped immediately or as soon as it is safe to do so, and resumed only in accordance with the statement. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A person conducting a business or undertaking that includes carrying out high risk construction work in connection with a construction project must, before the work commences, ensure that a copy of the safe work method statement is given to the principal contractor. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A person conducting a business or undertaking must ensure that a safe work method statement is reviewed and, as necessary, revised if relevant control measures are revised under regulation 38. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A copy of the safe work method statement must be kept until the high risk construction work is completed, or, if a notifiable incident occurs in connection with the work, for at least 2 years after the incident; for that period a copy must be readily accessible to any worker engaged to carry out the work and available for inspection under the Act. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A duty holder must eliminate risks so far as is reasonably practicable and, if that is not reasonably practicable, minimise them by substitution, isolation or engineering controls, then administrative controls for any risk that remains, then suitable personal protective equipment; a combination may be used. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A control measure must be reviewed and as necessary revised when it does not control the risk it was implemented to control so far as is reasonably practicable, before a change at the workplace likely to give rise to a new or different risk it may not effectively control, when a new relevant hazard or risk is identified, when the results of consultation indicate a review is necessary, and when a health and safety representative requests a review under r 38(4); a representative may request one if they reasonably believe that one of the circumstances in r 38(2)(a) to (d) affects or may affect the health and safety of a member of their work group and the duty holder has not adequately reviewed the control measure in response. Source: Work Health and Safety Regulations 2011 (Cth), the model regulations, legislation.gov.au F2011L02664, epub https://www.legislation.gov.au/F2011L02664/2026-11-18/2026-11-18/text/original/epub/OEBPS/document_1/document_1.html, Compilation date served 25 March 2025 (Compilation No. 28). Checked 2026-11-19 (Sydney).
- A person conducting a business or undertaking must, so far as is reasonably practicable, consult workers who are, or are likely to be, directly affected by a matter relating to work health or safety (s 47(1)); if the workers are represented by a health and safety representative, the consultation must involve that representative (s 48(2)); consultation is required when identifying hazards and assessing risks and when making decisions about ways to eliminate or minimise those risks (s 49(a) and (b)). Source: Work Health and Safety Act 2011 (Cth), the model Act. Checked 2026-11-19 (Sydney).
- Victoria has its own Occupational Health and Safety Act 2004, whose s 20 sets its duty to eliminate or reduce risks so far as is reasonably practicable; the page says only that Victoria has its own Act and regulations. Source: Occupational Health and Safety Act 2004 (Vic) s 20. Checked 2026-11-17 (Sydney).

## About this page

This is the Markdown version of the page at
https://www.employmentcompass.com.au/templates/swms
made from the same page file for language models and other readers that work best with plain text.

Last reviewed: not yet recorded

## About Employment Compass

Employment Compass is a business name of Progredi Pty Ltd ABN 47 667 125 788.

HR retainer: from $300 a month + GST. Pricing is at https://www.employmentcompass.com.au/pricing

The HR retainer is one plan, from $300 a month + GST, with everything included. Your price depends on the size of your organisation, and we confirm it before you start. Every client starts with a check of their HR and workplace safety.

Call [1300 144 002](tel:1300144002), email [info@employmentcompass.com.au](mailto:info@employmentcompass.com.au), or send an enquiry at https://www.employmentcompass.com.au/contact.

Offices:

- Sydney CBD, 11 York Street, Sydney NSW 2000
- Parramatta, Suite 4.01, 7 Charles Street, Parramatta NSW 2150
- Canberra, 7 Neptune Street, Phillip ACT 2606